Rasuwagadhi Hydropower Company Limited
Chakrapath Maharajgunj, Kathmandu, Nepal
info@rghpcl.com.np
+977-01-4371744 ,01-4371794
About
Rasuwagadhi Hydropower Company Limited
Rasuwagadhi Hydropower Company Limited (RGHPCL) is a subsidiary of Chilime Hydropower Company Limited (CHPCL) and was incorporated in August 2011 as a public limited company. It has planned to develop a new project - Rasuwagadhi Hydroelectric Project (RGHEP) having capacity of 111MW in Rasuwa district of Central Development Region.
The cost of the project is estimated to be NRs. 13,684.20 million excluding financial cost. A 50:50 debt-equity structure will be employed for financing this project.
The company will manage the debt requirement of the project from the Employer's Provident Fund (EPF) for which tri-partite loan arrangement has been signed between EPF, CHCPL and RGHPCL on 2068/08/22. The equity investment will be made through 51% promoter share and 49% public share. Chilime has 33% shareholding in RGHCL. The promoter share will be raised first then after public share.
The Share Structure of the Company
Key Features of the Project
Type of Project: |
Run-of-River (ROR) |
Design Discharge: |
80.00 m3/sec |
Gross Head: |
167.90 m |
Headworks: |
Diversion Weir with Undersluice and Side off lake Intake |
Desander type and size: |
Underground, 3–Chamber of size125m x15m x12m |
Tunnel Length & Size: |
4203m, Circular section of dia, 6m |
Powerhouse: |
Underground Type |
Turbine Type, Orientation & No.: |
Francis, Vertical Axis & 3 Nos. |
Unit Capacity: |
38.50 MW |
Generator Unit Capacity & Nos.: |
3 phase Synchronous AC, 3 x 43.75 MVA |
Installed Capacity: |
111 MW |
Annual Salable Energy: |
613.875 GWh |
Dry Energy: |
84.318 GWh |
Wet Energy: |
529.557 GWh |
Transmission Line Length/ Voltage: |
10 km,132 kV Double Circuit up to Chilime Hub |
Status of the Project
- Detailed project report of the project has been completed.
- Construction of Test Adit tunnel to investigate the geological condition of the underground powerhouse is in progress
- The EIA report has been approved from the Ministry of Environment.
- Land acquisition process is in progress to acquire land required for this project.
- PPA has been signed with NEA on November 14, 2011.
- The tri-partite loan agreement for the construction of project has been signed on 8 December, 2011 between RGHPCL, CHCPL and EPF.
- RGHPCL has planned to start the construction of RGHEP by January 2013 and targeted to complete the project by the end of December 2016.
- Request for proposal (RFP) for the selection of Consultant is in progress.
- Pre-qualification and tender document preparation is going simultaneously to construct RGHEP in EPC model.